Electricity is not just a basic utility—it is the foundation of modern life. Whether you're building a new home, opening a shop, or starting a farm, having access to power is a necessity. In Odisha, the government has made it easier than ever to apply for a new electricity connection, both online and offline.
This detailed blog post will guide you through every step, list required documents, explain costs, and give you official links to make your application process smooth and successful.
How to Apply for New Electricity Connection in Odisha: Full Guide (2025) - PSP Studio Odia |
⚡ Electricity Distribution in Odisha
Odisha's power distribution is managed by four major electricity companies under TPCODL (Tata Power Central Odisha Distribution Limited) and other zones:
Region | Company Name |
---|---|
Central Odisha | TPCODL (Bhubaneswar, Cuttack etc.) |
North Odisha | TPNODL (Balasore, Baripada etc.) |
South Odisha | TPSODL (Berhampur, Rayagada etc.) |
Western Odisha | TPWODL (Sambalpur, Rourkela etc.) |
These are all operated by Tata Power, ensuring a standardized and digital application process.
🧾 Types of Electricity Connections
You need to choose the correct type of connection before applying:
-
Domestic Connection: For homes and apartments
-
Commercial Connection: For shops, offices, hotels
-
Industrial Connection: For factories, production units
-
Agricultural Connection: For tube wells, irrigation pumps
-
Temporary Connection: For construction or short-term events
📄 Required Documents
Here is a complete list of documents you will need:
-
Identity Proof (Any one):
Aadhaar Card / Voter ID / PAN Card / Passport / Driving License -
Address Proof:
Aadhaar Card / Land Deed / Rent Agreement / Utility Bill -
Ownership Proof:
Patta / Khata / Land Registration Deed / NOC (if tenant) -
Photograph:
Passport-size photo of the applicant -
Load Requirement Details:
In kW or kVA (for industrial/commercial) -
Electrical Wiring Completion Certificate (optional in some areas)
🌐 How to Apply Online for New Connection in Odisha
The online application process is simple and convenient. Follow these steps depending on your region:
How to Apply for New Electricity Connection in Odisha: Full Guide (2025) - PSP Studio Odia |
✅ For TPCODL (Central Odisha)
Official Website: https://www.tpcentralodisha.com/
Step-by-Step:
-
Click on "New Connection" under Services
-
Register with your mobile and email
-
Choose your Connection Type (Domestic/Commercial/Industrial)
-
Fill in all required details
-
Upload the scanned documents (JPEG/PDF)
-
Submit the application
-
Receive an Application Number for tracking
-
Pay Application Charges (Online Payment Available)
-
Schedule site inspection
✅ For TPNODL (North Odisha)
Website: https://www.tpnodl.com
Follow same steps as above. Portal is designed similarly.
✅ For TPSODL & TPWODL
TPSODL: https://www.tpsodl.com
TPWODL: https://www.tpwesternodisha.com
Just visit their site → Click on “Apply for New Connection” → Proceed with digital form.
🏢 How to Apply Offline
If you’re not comfortable online, you can apply offline:
-
Visit your local Electric Subdivision Office
-
Collect the New Connection Application Form
-
Fill it carefully
-
Attach all required documents
-
Submit at the counter
-
Get a receipt with Application Number
-
Site inspection will be arranged
-
Pay the required fees in cash/bank
Tip: Keep one copy of your form and receipts for future tracking.
How to Apply for New Electricity Connection in Odisha: Full Guide (2025) - PSP Studio Odia |
💸 Application Fees and Security Deposit
The fee depends on your load and type of connection:
Type of Connection | Application Fee | Security Deposit |
---|---|---|
Domestic (Up to 2kW) | ₹100–200 | ₹500–2000 |
Commercial (Up to 5kW) | ₹500–1000 | ₹2000–5000 |
Industrial / Heavy Load | ₹1000+ | As per load |
Additional fees may include:
-
Line extension charges (if far from main pole)
-
Meter cost
-
Labour & materials
🔍 Site Inspection & Approval
Once your application is submitted:
-
A technician/engineer from the electricity board will visit your premises
-
They will check wiring, pole distance, meter board, and overall safety
-
Based on the inspection, they will approve or suggest changes
If everything is okay, you will get an approval email/SMS within 7–10 working days.
📦 Meter Installation & Connection Release
Once approved and fees paid:
-
An electrician will come to install the meter and cables
-
Power supply will be connected from the nearest pole
-
Meter reading and Consumer Number will be recorded
-
You can now start using electricity legally
You will also receive:
-
Connection certificate
-
Consumer ID / Account No.
-
Instructions on how to register for online billing
📲 Post-Connection Tips
-
Register for e-Billing:
Download the Tata Power app or register on the website. -
Pay Bills Online:
Avoid late fines, pay using PhonePe, Paytm, Google Pay, etc. -
Monitor Usage:
Use the online portal to check your usage in units and cost. -
Raise Complaints Online:
For outages or faults, use the official app or call 1912.
❓ Frequently Asked Questions
Q. How long does it take to get a new connection?
A. Usually 7–30 days depending on site inspection and paperwork.
Q. Can I apply without owning the land?
A. Yes, but you need a No-Objection Certificate from the landowner.
Q. What is the load limit for domestic connections?
A. Usually up to 5kW. For more, apply as commercial or request load upgrade.
Q. Can I transfer my connection if I move?
A. Yes, use the “Change of Name” option on the portal.
🔗 Useful Links
Service | Link |
---|---|
TPCODL | https://www.tpcentralodisha.com/ |
TPNODL | https://www.tpnodl.com |
TPSODL | https://tpsouthernodisha.com/ |
TPWODL | https://www.tpwesternodisha.com |
Odisha Electricity Complaints | https://www.odisha.gov.in |
Consumer Helpline (1912) | Call 1912 or local zone office |
👨💼 Author Profile
Author: PARTHASARATHI PANDA (M.Com)
A dedicated blogger, website designer, YouTube content creator, and social media influencer from India. With a Master’s degree in Commerce (M.Com), PARTHASARATHI PANDA creates and shares knowledge to help people grow digitally and personally.
Writes and speaks in English, Hindi, and Odia to support audiences across languages and regions. His mission is to empower everyone — from students to farmers — with free and useful content online.
✨ Connect with Me:
-
🌐 Website: FREE COMPUTER TRICKS
-
🌐 Blog: HELP ODIA & PSP STUDIO ODIA
-
🎥 YouTube:
- 📘 Facebook: Parthasarathi Panda
📢 Conclusion
Getting a new electric connection in Odisha has become faster, easier, and digital thanks to Tata Power’s reliable services across the state. Whether you choose to apply online or offline, following the steps above will ensure your application is approved smoothly.
Stay connected with me at HELP ODIA & PSP STUDIO ODIA for more useful guides!